Equipment Rigging ROM Calculator

Heavy equipment moves combine transport, crane/rigging, millwright labor, permits, insurance, and a contingency. This is a ROM (±25%), not a bid.

$21,850 – $42,375

Estimated range

  • Heavy-haul transport (200 mi)$1,600$4,000
  • Crane / rigging (8 hrs × 2 crews)$2,400$6,400
  • Millwright labor (5 days)$6,000$12,000
  • Permits / escorts (user input)$1,500$1,500
  • Cargo / riggers insurance (~1.5%)$7,500$10,000
  • ROM contingency (15–25%)$2,850$8,475

Rough-order-of-magnitude for industrial equipment relocation. Final bids require site survey, rigging plan, and carrier quotes.

How this is calculated

Heavy-haul per mile × distance, crane/rigging hours × crews, millwright labor, user-input permits, cargo insurance, and a ROM contingency of 10–25%.

Sources: rigging/millwright rate surveys; heavy-haul industry benchmarks. Compiled August 2025.

Example estimates: low, average, high

Computed with the same model as the calculator above — not hand-written. Your own inputs will differ.

ScenarioEstimated rangeWhat drives it
Light machine · short haul$3,910 – $7,750Light, 50 mi
Mid machine · regional haul$21,850 – $42,375Mid, 200 mi
Heavy plant · long haul + crews$146,740 – $243,500Heavy, 600 mi, 3 crews

Formula & data sources

Transport = heavy-haul $/mile × miles
+ Crane/rigging (hours × crews), + millwright (crew-days × 8 h × crews)
+ permits/escorts (your input), + cargo insurance (≈ % of equipment value)
+ ROM contingency (10–25%)

Sources: rigging/millwright rate surveys; heavy-haul industry benchmarks. Compiled August 2025.

When to use this calculator

  • Use this for industrial equipment or machinery relocation needing cranes, rigging, and millwrights.
  • Moving an entire office? Use Office Relocation for commercial scopes.
  • Building a new plant? See Facility Build-Out for the construction budget.

Frequently asked questions

What is a ROM?

Rough Order of Magnitude (±25%). It is a planning number; a real bid requires a site survey, rigging plan, and carrier quotes.

Why is insurance a line item?

Cargo and riggers' liability insurance scales with equipment value; we surface it so high-value moves aren't under-budgeted.

What is not included?

Engineering, specialized permits beyond your input, and temporary foundations are excluded. Enter known permit costs directly.

How are crews counted?

Crane and millwright labor multiply hours by crew count; large machines need multiple simultaneous crews, which the model reflects.

Why a contingency?

Industrial moves hit unforeseen access, weather, and equipment issues; a 10–25% ROM contingency is standard practice.